Official certified transcript

2026-02-03 · Planning Board

Imported from the Town’s original PDF. Speakers follow the printed labels. Citations use PDF pages rather than video timestamps.

Original certified PDF ↗ · Archived original ↓

Page 1 Original page ↗

      TOWN OF CORTLANDT

  PLANNING AND ZONING BOARDS




        BOARD MEETING




           Town Hall

        1 Heady Street

Cortlandt Manor, New York 1057

       February 3, 2026

    6:20 p.m. - 7:28 p.m.

Page 2 Original page ↗

                                                             Page 2
February 3, 2026

MEMBERS PRESENT:


     Steven Kessler, Chairman

     Thomas A. Bianchi, Vice Chairman

     Nora Hildinger, Member

     Kevin Kobasa, Member

     Peter McKinley, Member

     Jeff Rothfeder, Member

     Kellan Cantrell, Alternate



ALSO PRESENT:


     Chris Kehoe, AICP, Director of Planning

     Michael Cunningham, Esq., Deputy Town Attorney

     Heather LaVarnway, CNU-A, Planner

     Chris Lapine, P.E., Engineer

     Catherine Brosnan, P.E., Assistant Civil Engineer




                        Geneva Worldwide, Inc.
            228 Park Ave S - PMB 27669. New York, NY 10003

Page 3 Original page ↗

                                                             Page 3
1    February 3, 2026

 2   (The board meeting commenced at 6:20 p.m.)

 3             MR. STEVEN KESSLER:           All right, we’re

 4   going to get started. Welcome to the planning

 5   board meeting for February 3rd. Please rise for

 6   the pledge.

 7             MULTIPLE:       I pledge allegiance to the

 8   flag of the United States of America and to the

 9   republic for which it stands, one nation under

10   God, indivisible with liberty and justice for

11   all.

12             MR. KESSLER:        Roll please, Chris.

13             MR. CHRIS KEHOE:          Mr. Kobasa?

14             MR. KEVIN KOBASA:           Here.

15             MR. KEHOE:       Ms. Hildinger?

16             MS. NORA HILDINGER:           Here.

17             MR. KEHOE:       Mr. Rothfeder?

18             MR. JEFF ROTHFEDER: Here.

19             MR. KEHOE:       Mr. Kessler?

20             MR. KESSLER:        Here.

21             MR. KEHOE:       Mr. Bianchi?

22             MR. BIANCHI:        Here.

23             MR. KEHOE:       Mr. Cantrell?

24             MR. KELLAN CANTRELL:            Here.



                        Geneva Worldwide, Inc.
            228 Park Ave S - PMB 27669. New York, NY 10003

Page 4 Original page ↗

                                                             Page 4
1    February 3, 2026

 2               MR. KEHOE:     Mr. McKinley?

 3               MR. PETER MCKINLEY:         Here.

 4               MR. KESSLER:      Thank you. So this

 5   evening, one change to the agenda which we

 6   notified the public about, we’ll be not, having

 7   the yeshiva tonight on the agenda. Chris sent out

 8   notifications to interested parties and it was in

 9   the town newsletter, the weekly newsletter, also

10   made note of that. So, if there’s anybody here

11   for the yeshiva, we will not be discussing that

12   this evening. It’ll be back on the agenda for our

13   March 3rd meeting. Can I please have a motion to

14   adopt the minutes from our meeting of January

15   6th?

16               MR. MCKINLEY:        So moved.

17               MR. KESSLER:      Thank you. Second?

18               MR. KOBASA:      Second.

19               MR. KESSLER:      And on the question, all

20   in favor?

21               MULTIPLE:     Aye.

22               MR. KESSLER:      Opposed? First item is to

23   receive and file the 2025 annual report of the

24   planning board.



                        Geneva Worldwide, Inc.
            228 Park Ave S - PMB 27669. New York, NY 10003

Page 5 Original page ↗

                                                            Page 5
1    February 3, 2026

 2               MR. ROTHFEDER:       Mr. Chair, I move that

 3   we receive and file this report.

 4               MR. KESSLER:     Okay. Second, please.

 5               MR. BIANCHI:     Second.

 6               MR. KESSLER:     And on the question. All

 7   in favor?

 8               MULTIPLE:    Aye.

 9               MR. KESSLER:     Opposed? Okay. First item

10   is a resolution, it’s the application of 2051

11   Cortlandt Holding, LLC, for amended site plan

12   approval for the addition of five parking spaces

13   at the existing gas station located at 2051 East

14   Main Street, drawing latest revised December 22,

15   2025. Kevin?

16               MR. MCKINLEY:       I’d like to make a motion

17   to adopt resolution 5-26.

18               MR. KESSLER:     Thank you. Second, please.

19               MR. ROTHFEDER:       Second.

20               MR. KESSLER:     And on the question, all

21   in favor?

22               MULTIPLE:    Aye.

23               MR. KESSLER:     Opposed? Okay. Next item

24   is adjourn, as I mentioned, we’re skipping over



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 6 Original page ↗

                                                            Page 6
1    February 3, 2026

 2   the yeshiva this evening. The next item is an

 3   adjourned public hearing. It’s the public hearing

 4   for the application of VS Construction

 5   Corporation for site plan approval and for tree,

 6   wetland and steep slope permits for a proposed

 7   96,850 square foot assisted living facility

 8   located in the medical oriented district at 2003

 9   Crompond Road, latest drawings November 20, 2025.

10   Mr. Steinmetz, good evening.

11            MR. DAVID STEINMETZ: Good evening, Mr.

12   Chairman, members of the board, David Steinmetz

13   from the law firm of VS -- from the law firm of

14   VS, law firm of Zarin and Steinmetz --

15            MR. KESSLER:        It might as well be.

16            MR. STEINMETZ:         -- representing VS

17   Construction. Maybe Mr. Santucci would like me to

18   join his law firm but, the good news is I have

19   Mr. Schwartz as a partner rather than Mr.

20   Santucci. Here tonight in connection with the

21   assisted living application that we have

22   previously appeared on, our client has a

23   development site that we have explained to you.

24   Benchmark Senior Living is interested in placing



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 7 Original page ↗

                                                            Page 7
1    February 3, 2026

 2   a 100-unit, 118-bed assisted living facility. I

 3   believe William Cook from Benchmark is on screen

 4   if we have any specific questions.

 5            This is a continuation of our public

 6   hearing on this project, and I’m going to take

 7   one step back. As I mentioned in the work

 8   session, this site was the subject of a

 9   comprehensive review pursuant to the New York

10   State Environmental Quality Review Act, SEQRA, in

11   connection with the medical oriented district,

12   the MOD rezoning process. We are now here

13   specifically in the northeast corner of the MOD

14   with regard to this particular site.

15            We have presented this to you. As we

16   indicated at the last, the kickoff session of the

17   public hearing, we had received a number of

18   comments from your board and from staff about

19   reorienting, reorienting aspects of that

20   building. We have done that. We have also

21   conducted a fairly comprehensive site inspection

22   with your board and staff, where we looked at the

23   site, the trees, the wetland area, and in

24   particular, the corner of the property where



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 8 Original page ↗

                                                            Page 8
1    February 3, 2026

 2   there are some retaining walls.

 3               We, my client and Benchmark’s design

 4   team have attempted to be responsive to the

 5   concerns that have been raised. And we’re here

 6   tonight, Matt Steinberg is going to do a brief

 7   presentation. We have responded to comments that

 8   we have received from DOTS, from your outside

 9   engineering consultant and most recently we have

10   received some comments from the Westchester

11   County planning department under Section 239M of

12   the general municipal law.

13               We understand that there may still be

14   some technical issues that are going back and

15   forth between our consultants and the town. But

16   we’re pleased that we’re making significant

17   progress. And I can tell you that Benchmark and

18   VS Construction are anxious to bring this to

19   fruition.

20               This is one of the linchpins of what

21   Envision Cortlandt had in mind 10 years ago when

22   your comprehensive planning committee wanted to

23   bring medical uses that combined both residential

24   accommodation, i.e. housing for seniors, as well



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 9 Original page ↗

                                                            Page 9
1    February 3, 2026

 2   as the provision of activities of daily living

 3   support and services. Benchmark is one of the

 4   preeminent providers of senior services in this

 5   region, and they are very excited as, as are we,

6    to bring them to the Cortlandt community. So,

7    with that, I’m going to turn it over to Matt.

8               MR. KESSLER:      Just one question before

9    you do that.

10              MR. STEINMETZ:       Sure.

11              MR. KESSLER:      The plans we received this

12   evening, those are in response to Mr. Lapine’s

13   memo of January 21st?

14              MR. STEINMETZ:       So the plans that are,

15   that you have this evening are probably from the

16   last round of comments that we got from Chris. I

17   would --

18              MR. KEHOE:     Yeah. Just, the planning

19   department issued a review memo January 16th, and

20   Chris Lapine issued one January 20th.

21              MR. STEINMETZ:       Correct.

22              MR. KESSLER:      21st.

23              MR. KEHOE:     Yeah.

24              MR. STEINMETZ:       So we’re good. But we



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 10 Original page ↗

                                                             Page 10
1    February 3, 2026

 2   didn’t turn it around that quickly. We just got,

 3   we just got his, his memo like a week and a half

 4   ago.

 5             MR. KESSLER:        Okay. So, basically more

 6   revisions to come is my point.

 7             MR. STEINMETZ:         Which is why I said we

 8   know there are still some technical issues that

 9   have to be addressed. But the, we appreciate the

10   fact that staff has been moving with us and, and

11   proceeding. As we generate more iterations,

12   they’re conducting their review and getting back

13   to us, again, all in an effort to finally bring

14   the MOD to fruition.

15             So there’s a number of technical issues

16   that have been confronted. We, I think, addressed

17   and got rid of the wetland concern that, that

18   arose several months ago. We addressed, and we

19   think we got rid of the retaining wall issue that

20   arose several months ago. So we are, we’re sort

21   of down to the short straws at this point, but

22   that remains to be seen. And at least allow Matt

23   to respond to some of these comments and address

24   some of the county comments as well.



                        Geneva Worldwide, Inc.
            228 Park Ave S - PMB 27669. New York, NY 10003

Page 11 Original page ↗

                                                            Page 11
1    February 3, 2026

 2              MR. KESSLER:      Okay. I also, we wanted, I

 3   thought the fire department was also going to go

 4   out there. Has that happened?

 5              MR. KEHOE:     No. Fire department did the

 6   yeshiva.

 7              MR. STEINMETZ:       Yeah, we did, we talked

 8   about that on other matters. Katie, you would

 9   know better than I. I thought we were talking

10   about that on the --

11              MS. KATIE BROSNAN:         On the, the fire --

12              MR. KESSLER:      It was on the yeshiva?

13              MR. STEINMETZ:       On the, on the yeshiva

14   and the self-storage.

15              MR. KESSLER:      Oh, okay.

16              MS. BROSNAN:      Yeah. But they haven’t, I

17   don’t think they’ve gone to self-storage.

18              MR. KESSLER:      Okay. Okay. Then --

19              MS. BROSNAN:      But they did the yeshiva.

20              MR. KESSLER:      -- we’ll deal with that

21   next time.

22              MR. STEINMETZ:       Got it. Got it.

23              MR. CHRIS LAPINE:        I think you’re, Mr.

24   Chairman, I think you’re referring to the fire



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 12 Original page ↗

                                                            Page 12
1    February 3, 2026

 2   department reviewing the slopes at the main

 3   entryway into the site, you wanted that

 4   revisited.

 5            MR. KESSLER:        I’m sorry, I missed that?

 6            MR. LAPINE:        I think you’re referring to

 7   the slopes at the front of the site.

 8            MR. KESSLER:        Yes.

 9            MR. LAPINE:        For this application, it

10   was about 10 percent slope and you wanted to

11   confirm from the fire department that they can

12   make those slopes, so.

13            MR. STEINMETZ:         I thought that issue was

14   addressed in SEQRA, Chris, but we can confirm.

15            MR. KESSLER:        Okay.

16            MR. MATT STEINBERG:           Thank you, David.

17   Matt Steinberg, DTS Provident. So yeah, we are in

18   the process of responding to the planning

19   department’s comments and to the engineering

20   department, engineering comments. So we’re, you

21   know, we will be submitting another set of plans

22   to address those comments. Regarding fire, we had

23   addressed that in the previous set, but

24   obviously, you know, if there’s additional



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 13 Original page ↗

                                                            Page 13
1    February 3, 2026

 2   comments to be had from the fire department,

 3   we’ll obviously address them. But, we did address

 4   their comments regarding, slopes into the site,

 5   through the parking lot. And then, a fire truck

 6   in this instance can circulate all the way

 7   through the site, out the emergency access back

 8   to Crompond Road.

 9            What we did submit to this board is,

10   response to the Westchester County comments. They

11   had a number of comments. Some of them had to do

12   with the overall Evergreen site, so we tried to

13   be responsive to those. One in particular had to

14   do with parking spaces. So the number of parking

15   spaces is a little bit over what is required

16   under the code.

17            This was just, essentially based to be

18   consistent with ITE, the Institute of

19   Transportation Engineers, requirements or

20   suggestions, along with what Benchmark feels

21   comfortable with for their staff and guests. It’s

22   only, it’s not a ton, 66 parking spaces, 59 are

23   required. So, it’s not an excessive amount over.

24   We did actually remove some spaces to provide



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 14 Original page ↗

                                                            Page 14
1    February 3, 2026

 2   additional room for maneuvering in response to

 3   some of the comments that we’re working through

 4   from staff.

 5            We’ll take another look whether or not

 6   any other spaces would be removed. Essentially

 7   the parking lot though, the way it’s configured,

 8   there’s really, we wouldn’t be reducing the

 9   impervious as part of that though. That was

10   really, I mean, I’m happy to answer any questions

11   if you have.

12            MR. KESSLER:        Well, I guess the other

13   comments from the county regarding the bus stop

14   and the sidewalks, right. Those are the other two

15   issues that they raised?

16            MR. STEINBERG:         They did, They did raise

17   that. So there was a bus stop as part of the

18   overall transportation improvements along the

19   corridor. So the bus stop that’s actually closer

20   to the hospital is going to be relocated slightly

21   and improved. So it’ll have an improved turnoff

22   for buses. That --

23            MR. KESSLER:        You had that discussion

24   with the county?



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 15 Original page ↗

                                                            Page 15
1    February 3, 2026

 2            MR. STEINBERG:         We have not had a

 3   discussion further with the county as far as a

 4   bus stop closer to our site. We’re going to try

 5   to set that up with them.

 6            MR. KESSLER:        Okay.

 7            MR. STEINBERG:         In previous --

 8            MR. KEHOE:       But Matt, is some of the bus

 9   stop stuff worked in with what Colliers is doing

10   on the transportation improvements?

11            MR. STEINBERG:         Correct.

12            MR. KEHOE:       Right.

13            MR. STEINBERG:         Correct, right. As part

14   of those overall improvements, there’s an

15   improvement to the existing bus stop that serves

16   an existing line.

17            MR. LAPINE:        And, and Matt, if I’m

18   correct from the meeting that we had, some of

19   this is related to existing utilities that are

20   prohibiting relocation of that bus stop even

21   closer to the site? From what Colliers explained

22   to us during that meeting?

23            MR. STEINBERG:         Yes. Yes.       There are

24   some existing poles, not in front of the VS site,



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 16 Original page ↗

                                                            Page 16
1    February 3, 2026

 2   but in front of the Gyrodyne site that actually

 3   serve the hospital and they can’t be relocated

 4   readily. So --

 5            MR. KESSLER:        The bus stop is currently

 6   at the Gyrodyne site?

 7            MR. STEINBERG:         It’s closer to the

 8   Gyrodyne site.

 9            MR. KESSLER:        But You mentioned you were

10   going to move it?

11            MR. STEINBERG:         It was going to slightly

12   move a little bit closer to our site, but still

13   in front of the Gyrodyne site, that’s still where

14   it makes sense.

15            MR. KESSLER:        The county has to approve

16   that movement.

17            MR. STEINBERG:         Hmm?

18            MR. KESSLER:        Doesn’t the county have to

19   approve moving the bus stop?

20            MR. STEINBERG:         Um --

21            MR. KEHOE:       I think the county Bee-Line

22   might have to.

23            MR. STEINBERG:         They, yeah, they might

24   as part of the review of the Collier’s



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 17 Original page ↗

                                                            Page 17
1    February 3, 2026

 2   transportation plans. But overall, the intent is

 3   to, to improve it so it’ll have a larger pull off

 4   for a bus as part of that. So I, you know, we’re

5    hoping that that is seen as a benefit. The --

 6            MS. HILDINGER:         It still west Of

 7   Lafayette though?

 8            MR. STEINBERG:         It is west of Lafayette.

 9            MR. MCKINLEY:         It’s where the

10   [unintelligible] [00:12:11] are.

11            MR. STEINBERG:         Yep. And it is, I think

12   I, we included --

13            MR. KESSLER:        It’s basically across from

14   the hospital right now.

15            MR. STEINBERG:         Yes. Which, you know,

16   the, the hospital certainly has the larger

17   ridership.

18            MR. KESSLER:        Sure.

19            MR. STEINBERG:         In past, and we’ll try

20   to have a discussion with, with the Department of

21   Transportation at the county. In the past,

22   obviously these lines are very long, these Bee-

23   Line buses. Obviously, adding additional stops

24   adds additional times to very long lines.



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 18 Original page ↗

                                                               Page 18
1    February 3, 2026

 2               MR. KESSLER:        Sure.

 3               MR. STEINBERG:         They tend to typically

 4   do not just do that without, you know, having a

 5   known ridership. You know, the, while there will

 6   be a population at this site, it probably does

 7   not warrant another stop at this time. The Bee-

 8   Line obviously will investigate that. But we’ll

 9   have that discussion with them.

10               MR. KESSLER:        But there will be a

11   sidewalk going from your side to that bus stop?

12               MR. STEINBERG:         Correct, which doesn’t

13   exist today. So there’ll be that new sidewalk.

14   The county kind of mentioned crosswalks, so part

15   of this, there would be crosswalks, there’ll be

16   new crosswalks across Lafayette. There’ll be a

17   new crosswalk across Crompond Road to the

18   hospital. So there’s a, there’s a number of

19   improvements in the, in the roadway improvement

20   plans.

21               MR. KESSLER:        But they also raised the

22   issue of the sidewalk going east?

23               MR. STEINBERG:         They did.

24               MR. KESSLER:        And your position is?



                          Geneva Worldwide, Inc.
              228 Park Ave S - PMB 27669. New York, NY 10003

Page 19 Original page ↗

                                                            Page 19
1    February 3, 2026

 2               MR. STEINBERG:      That it does not really

 3   provide additional access to anywhere else. It

 4   would get to the end of our site, perhaps. The

 5   likelihood of putting another crosswalk to the

 6   nearby commercial is probably very difficult.

 7   That would be a midblock crossing on a state

 8   road. We just don’t see that that would happen.

 9               MR. KESSLER:     Would that be by Conklin

10   or?

11               MR. STEINBERG:      Further east of Conklin.

12   I don’t, sorry, I’m not sure, I don’t remember

13   the road.

14               MR. KESSLER:     Will there be a crosswalk

15   going to Conklin or from your site, no?

16               MR. STEINBERG:      No. There will not be --

17   I don’t think there’s a crosswalk proposed there.

18               MR. KESSLER:     So the only crosswalk will

19   be across Lafayette into the hospital?

20               MR. MCKINLEY:      Right here.

21               MR. KOBASA:     Across Crompond?

22               MR. STEINBERG:      Yes. To the hospital and

23   then again, over by the Gyrodyne entrance, I

24   think there’s another set of crosswalks. So



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 20 Original page ↗

                                                            Page 20
1    February 3, 2026

 2   there’ll be additional crosswalks, additional

 3   sidewalks, additional, definitely additional

 4   mobility between our site, the future Gyrodyne

 5   and the hospital itself plan.

 6             MR. MICHAEL CUNNINGHAM:            Matt, isn’t

 7   Collier’s engineering working on the plans too,

 8   and, and speaking with the county and the state

 9   about that as well? Or is that just your team

10   specifically?

11             MR. STEINBERG:        No. Colliers is the one

12   working on the roadway improvements. They are

13   definitely in concert with the state, because it

14   obviously is a DOT road, but also with the county

15   because Dayton Lane, that intersection, the

16   existing, and I think the light after that is

17   county. So there’s a coordination between all

18   parties, both the town, the county, and the

19   state. Our understanding is that the lights will

20   all be hooked to the same system so that they

21   will communicate with each other. So that’s being

22   discussed now so that they’re coordinated between

23   the county’s and the state’s highway signal

24   system.



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 21 Original page ↗

                                                            Page 21
1    February 3, 2026

 2            MR. CUNNINGHAM:          And, just by way of

 3   review too, the Colliers is a town retained

 4   consultant and it’s being funded by VS

 5   Construction and Gyrodyne. So they’re the one

 6   that’s overseeing all the developments and the,

 7   all the improvements to the road and the

 8   sidewalks and the crosswalks and the corridor,

 9   because it had to be aligned. You couldn’t just

10   ha look at each project piecemeal, because then

11   it would end up with just, with improvements that

12   didn’t make sense for the whole corridor.

13            MR. STEINMETZ:         So, very much appreciate

14   Michael’s comments and taking a step back,

15   because more than half of this board was not

16   sitting on this board at the time we went through

17   the MOD, a four-year SEQRA process, which

18   culminated in a finding statement that Michael’s

19   alluding to with literally several million

20   dollars of offsite improvements that are required

21   to be made at neighboring intersections,

22   crosswalks, road widenings, et cetera.

23            But the most important point Michael

24   made is it took into account not only the



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 22 Original page ↗

                                                               Page 22
1    February 3, 2026

 2   Evergreen site and everything we’re talking about

 3   tonight, the assisted living, and you heard

 4   during the work session, 96 townhouse lots as

 5   well as a 10,000 square foot commercial building,

 6   which we’ll get to later on the agenda. But it

 7   also took into account a rather sizable project

 8   at the Gyrodyne property. So all of those

 9   improvements were all mandated mitigation as part

10   of the full SEQRA process. And yes, the

11   applicants, Gyrodyne and VS Construction are

12   required to implement those.

13               MR. KESSLER:        Okay. Go ahead. Sure, Tom?

14               MR. BIANCHI:        Is Crompond Road a state

15   road? Okay. Has there been, or have you received

16   comments from the DOT on traffic mitigation

17   measures that, except for, I know there’s

18   Lafayette, there’s modifications going on there,

19   but --

20               MR. STEINMETZ:         So we received --

21               MR. BIANCHI:        I don’t recall seeing

22   them.

23               MR. STEINMETZ:         So Tom, that was all

24   baked into, literally two years of your



                          Geneva Worldwide, Inc.
              228 Park Ave S - PMB 27669. New York, NY 10003

Page 23 Original page ↗

                                                            Page 23
1    February 3, 2026

 2   consultants working with DOT during the SEQRA

 3   process.

 4              MR. BIANCHI:      Okay.

 5              MR. STEINMETZ:       So DOT, everything that

 6   I just referred to in terms of the, the several

 7   million dollars of offsite improvements, those

 8   are mandates from DOT.

 9              MR. BIANCHI:      Okay.

10              MR. STEINMETZ:       They were coordinated

11   with the town’s consultant. The town at that time

12   was utilizing AKRF as its traffic consultant and

13   its SEQRA consultant. So all of that was studied

14   in the DEIS, the FEIS and the town board as lead

15   agency under SEQRA, mandated those mitigation

16   measures and they’re baked into the finding

17   statement that bind all of us.

18              MR. BIANCHI:      Okay. Are there, I don’t

19   recall. I’m not doubting you, I just don’t recall

20   seeing them, but are there measures --

21              MR. STEINMETZ:       You ask Michael, you

22   don’t have to ask me. C

23              MR. BIANCHI:      -- at the cross section,

24   the intersection of the site and Crompond Road



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 24 Original page ↗

                                                              Page 24
1    February 3, 2026

 2   other than Lafayette? Are there any --

 3              MR. STEINMETZ:         Dayton Lane --

 4              MR. BIANCHI:        -- additional light, near

 5   Conklin, for instance?

 6              MR. STEINMETZ:         Dayton Lane, Lafayette

 7   Conklin, road widening on 202, crosswalks.

 8              MR. STEINBERG:         And the Bear Mountain

 9   Parkway --

10              MR. BIANCHI:        Okay.

11              MR. STEINBERG:         -- intersection.

12              MR. BIANCHI:        Those were all addressed,

13   okay.

14              MR. STEINMETZ:         All studied and all

15   mitigated.

16              MR. BIANCHI:        All right. Thank you.

17              MR. KESSLER:        Okay. Any other questions

18   from the board or staff? And it’s, this is a

19   public hearing, is there anybody that wishes to

20   comment in the audience?

21              MR. LAPINE:        Mr. Chairman, just for your

22   benefit and the benefit of the board, we made one

23   aesthetic comment that maybe you can guide the

24   applicant on. At the northwest corner of the



                         Geneva Worldwide, Inc.
             228 Park Ave S - PMB 27669. New York, NY 10003

Page 25 Original page ↗

                                                            Page 25
1    February 3, 2026

 2   facility at the entry road, there is a retaining

 3   wall that’s being proposed, it’s 14 foot in

 4   height. Our office, I think along with planning,

 5   recommended the terracing of that wall so that we

 6   can incorporate some greenery there. Maybe if you

 7   can give the applicant some guidance, as that’s,

 8   that’s something that you wish to see.

 9            MR. KESSLER:        That’s on, the wall’s on

10   Crompond Road?

11            MR. LAPINE:        Yeah, it’s the, at the

12   intersection of the main entryway.

13            MR. KESSLER:        Okay.

14            MR. STEINMETZ:         So before Matt speaks to

15   that, I just want to state for the record that

16   just because I want to make a record on this,

17   it’s the second public hearing in a row that

18   nobody spoke to the assisted living. So I’m

19   pleased to see that. And, and I just want the

20   record to reflect that. But on the, the terracing

21   of the retaining wall, Matt, I thought we had

22   incorporated that?

23            MR. STEINBERG:         Well, we’ve, right. We

24   have incorporated some terracing. That front wall



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 26 Original page ↗

                                                               Page 26
1    February 3, 2026

 2   obviously is, as it appears in the image. So we

 3   were asked to investigate it. We are, we’re all

 4   looking at options. You know, this is, it’s a

 5   tight site, between the building and the setback.

 6   So there’s a limit of where we can set the wall

 7   and terrace it. There’s also a limit of how much

 8   planting we can do in the terracing itself,

 9   between each terrace. Obviously we, we would not

10   be able to plant trees, those wouldn’t work, but

11   they would’ve to be shrubs, whereas we could try

12   to put larger trees at the bottom of the base.

13   The further we move those terraces out, it just

14   limits how much space we have for those larger

15   trees. So we’re looking at it now so we can

16   present that back to staff.

17               MR. KESSLER:        Okay. And before Jeff

18   raises it, the county also raised the issue of

19   green building technology. Any, any thoughts, any

20   plans?

21               MR. STEINBERG:         So we’ve asked

22   Benchmark, if there’s anything specific, so we

23   can get back to you about that, yeah.

24               MR. KESSLER:        Okay.



                          Geneva Worldwide, Inc.
              228 Park Ave S - PMB 27669. New York, NY 10003

Page 27 Original page ↗

                                                            Page 27
1    February 3, 2026

 2            MR. ROTHFEDER:         Thank you.

 3            MR. KESSLER:        Okay. Yeah, I think that

 4   would be something to look into.

 5            MR. STEINMETZ:         Understood. We know Jeff

 6   would’ve raised it.

 7            MR. ROTHFEDER:         It was on my mind.

 8            MR. KESSLER:        Okay. Any other comments

 9   from the board of staff? So as, as you mentioned

10   David, so this, obviously still some work to be

11   done, so, we’ll be, adjourning this public

12   hearing to the March 3rd meeting. So, no other

13   comments, Kellan?

14            MR. KEHOE:       Just, you know, what, what,

15   what we’re talking about a lot recently is that

16   the, your team should get those revised drawings

17   back to us in advance of the deadline, not use

18   the deadline as their goal.

19            MR. STEINMETZ:         I got, I hear you.

20   You’ve been making that very clear to us on a

21   number of different applications to make sure you

22   have time to review it, and we can actually

23   accomplish something at the next meeting, got it.

24            MR. KESSLER:        Okay, motion, please.



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 28 Original page ↗

                                                            Page 28
1    February 3, 2026

 2               MR. CANTRELL:       Motion to adjourn the

 3   public hearing to the March planning board

 4   meeting.

 5               MR. KESSLER:     Thank you. Second, please.

 6               MR. BIANCHI:     Second.

 7               MR. KESSLER:     And on the question. All

 8   in favor?

 9               MULTIPLE:    Aye.

10               MR. KESSLER:     Opposed? Okay.

11               MR. STEINMETZ:       Thank you all.

12               MR. KESSLER:     See you then. All right,

13   moving on to old business this evening, it’s the

14   application of 70 Roa Hook Realty, LLC for, site

15   development plan approval to redevelop the site

16   of the partially constructed Crystal Clean

17   Carwash facility to a proposed vehicle showroom

18   and service facility for the property located at

19   70 Roa Hook Road, drawings dated January 22,

20   2026. Good evening.

21               MR. BRAD SCHWARTZ:        Good evening. Mr.

22   Chairman, members of the board and staff, Brad

23   Schwartz from the law firm still known as Zarin

24   and Steinmetz. So we’re here for an application



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 29 Original page ↗

                                                            Page 29
1    February 3, 2026

 2   for, to allow part sales and service repair of

 3   Peterbilt trucks at the property. When we were

 4   here in December, we had talked about bifurcating

 5   the approvals for those two operations. As you

 6   discussed in your work session, we talked to

 7   staff and we are now combining it. It’s one

 8   complete application covering both operations. We

 9   submitted a full site plan application covering

10   those uses with a full set of site plans. And we

11   look forward to comments and review by staff.

12            You should know that John Canning is now

13   also part of our team. I’m going to be submitting

14   a traffic parking report in the next day or two,

15   concluding that this will be a, a lesser impact

16   from traffic and parking as compared to the

17   proposed car wash.

18            MR. KESSLER:        He’s with you guys now?

19            MR. SCHWARTZ:         He’s with us, yeah, part

20   of the law firm too. Wow.

21            MR. KEHOE:       Oh, we used to use John

22   Canning, but I don’t think he was ever uniformly

23   on the municipal side. I do think he had been

24   representing private clients as well. He was



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 30 Original page ↗

                                                              Page 30
1    February 3, 2026

 2   never our personal consultant, so to speak.

 3              MR. CUNNINGHAM:          He represented the gas

 4   station recently on Route 6.

 5              MR. KESSLER:        Okay.

 6              MR. KEHOE:       Yeah.

 7              MR. CUNNINGHAM:          The one, the Sinclair

 8   station.

 9              MR. KESSLER:        Hmm. Okay. So as you said,

10   we’re going to refer this back for staff to --

11              MR. SCHWARTZ: John Gilchrist is here

12   tonight to make a brief presentation if you woud

13   like.

14              MR. KESSLER:        Oh, sure.

15              MR. SCHWARTZ:         So, just to point out the

16   modifications from the approved car wash and to

17   show you what we’re proposing to install.

18              MR. KESSLER:        Sure.

19              MR. JOHN GILCHRIST:           Good evening. I’m

20   John Gilchrist. I was the architect and engineer

21   for the car wash project. And the current owners

22   were good enough to rehire me to work with them

23   on this remodeling and addition of the project.

24   And, I wonder if you could put up my zoning plan,



                         Geneva Worldwide, Inc.
             228 Park Ave S - PMB 27669. New York, NY 10003

Page 31 Original page ↗

                                                            Page 31
1    February 3, 2026

 2   who’s in charge there? And then, yes, over to

 3   the, nope, the site plan part.

 4            Anyway, we, if you’re probably familiar

 5   with the car wash, it’s 90 percent complete and

 6   abandoned for several years. Our proposal is to

 7   remove, towards the front, two of the car wash

 8   bays and the rotunda, and then create a new

 9   building in addition that would serve as four

10   service bays.

11            Unfortunately, the car wash was designed

12   to accommodate a truck, but these service bays

13   need to fit a truck plus a crane rail above the

14   truck so that we could lift motors if necessary.

15   To the right and the rear, we have car wash bays

16   that will remain. We’re going to make them, the

17   two leftmost bays longer, again to accommodate a

18   longer truck. But otherwise, those bays will

19   stay, the existing office space will stay and

20   there’s, another wash bay that will remain that

21   we will use for parts storage.

22            MR. KESSLER:        So that’s seven bays

23   altogether, is that --

24            MR. GILCHRIST:         We have seven new bays,



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 32 Original page ↗

                                                             Page 32
1    February 3, 2026

 2   yes.

 3             MR. KESSLER:        Okay.

 4             MR. GILCHRIST:         Seven service bays.

 5   According to the letter produced by the operator,

 6   we have a very low incidence of trucks coming and

 7   going to the tune of 14 a month. That’s two per

 8   bay per month. When it was a car wash, we were

 9   anticipating at the peak morning hour, 20 cars

10   per hour and then evening peak hour, 40 cars per

11   hour, so easily in excess of a hundred cars a

12   day. So our traffic volume is greatly reduced.

13             Number of employees is about six, with

14   one guy who’s going to deliver parts. So our

15   parking requirement is reduced. We tried to fit

16   15 cars on the site, which is what was approved

17   for the car wash. We don’t need the 15 cars.

18   Otherwise that’s, that’s, pretty much what it is.

19   The, the site --

20             MR. ROTHFEDER:         Is of the business

21   deliveries?

22             MR. GILCHRIST:         We deliver parts. We’ll

23   receive parts and deliver parts.

24             MR. ROTHFEDER:         And then deliver?



                        Geneva Worldwide, Inc.
            228 Park Ave S - PMB 27669. New York, NY 10003

Page 33 Original page ↗

                                                            Page 33
1    February 3, 2026

 2               MR. GILCHRIST:      So if another service

 3   facility needs a specific part --

 4               MR. ROTHFEDER:      Right.

 5               MR. GILCHRIST:      -- we’ll, we’ll have it

 6   and we’ll deliver it.

 7               MR. ROTHFEDER:      Okay.

 8               MR. GILCHRIST:      May we’re not doing

 9   small services on trucks, we’re doing major

10   services.

11               MR. ROTHFEDER:      Mm-hmm.

12               MR. KESSLER:     So those trucks would

13   probably stay there for a number of days before

14   they leave?

15               MR. GILCHRIST:      They could be there for

16   two weeks.

17               MR. KESSLER:     Weeks, okay.

18               MR. GILCHRIST:      Yes.

19               MR. LAPINE:     Do you have to change any

20   of the, mitigation of the water, the drainage

21   because of a car wash would take water in? This

22   is going to be, you want to avoid that with oils

23   and other things.

24               MR. GILCHRIST:      We, we have, you know,



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 34 Original page ↗

                                                               Page 34
1    February 3, 2026

 2   all the underground stuff is done. The well is

 3   in, the septic is in all of the rainwater

 4   detention is in. We don’t need it. We don’t need

 5   the rainwater detention, but we have it, so that,

 6   all that stuff will work. The drainage of the

 7   site, the grading of the site will remain pretty

 8   much the same. It all drains through an oil water

 9   separator and then to an existing pipe under Roa

10   Hook Road out into Anneville Creek. So the

11   coverage of the site changes very little. The

12   drainage characteristics of the site changes very

13   little. The use of the site is way diminished.

14   And --

15               MR. KESSLER:        I’m out of my depth here.

16   But do you require additional oil separators or

17   something because of the work that you’re doing

18   on these trucks? I mean a car wash is one thing

19   where you’re just recycling the water. Here,

20   there’ll be other liquids that are going to be

21   generated and have to be captured and disposed

22   of?

23               MR. GILCHRIST:         It’s in, that’ll all be

24   inside the building.



                          Geneva Worldwide, Inc.
              228 Park Ave S - PMB 27669. New York, NY 10003

Page 35 Original page ↗

                                                            Page 35
1    February 3, 2026

 2            MR. LAPINE:        Interior.

 3            MR. GILCHRIST: But yeah, we, we’ll do

 4   oil changes and we’ll have to capture the oil,

 5   certainly. And that’ll be done according to state

 6   laws. There should be no, you know, less, we’re

 7   not going to have cars come out onto the parking

 8   lot to drip dry. It’s nothing like that.

 9            MR. KESSLER:        Is there a state review

10   process of this at all? Or of the facility or?

11            MR. GILCHRIST:         Certainly, you know, I’m

12   not aware, to tell you the truth.

13            MR. ROTHFEDER:         So we don’t know. Do

14   they come out and inspect like once a month or

15   that like the separators are working and that

16   sort of thing?

17            MR. GILCHRIST:         Are you subject to it?

18            UNIDENTIFIED MALE:           There’s a state

19   licensing requirement.

20            MR. GILCHRIST:         Yeah, so there’s a state

21   licensing requirement for this operation.

22            MR. ROTHFEDER:         But ongoing inspections

23   by the state?

24            UNIDENTIFIED MALE:           I don’t think so.



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 36 Original page ↗

                                                            Page 36
1    February 3, 2026

 2            MR. GILCHRIST:         No.

 3            MR. ROTHFEDER:         That’s great.

 4            MR. KEHOE:       But I think Katie do, do we

 5   do something with oil and water? Do we mandate

 6   reports from them or something like that? Okay.

 7   We’ll get that answer to you.

 8            MR. KESSLER:        Okay.

 9            MR. KEHOE:       Because they only work well

10   if they’re maintained.

11            MR. ROTHFEDER:         Yeah, exactly.

12            MR. LAPINE:        There’s in the building

13   code, this is similar to what we had to do with

14   the Hertz Rent-a-Car. There’s a whole process for

15   how they design these oil water separators, in

16   each particular bay and what their capacity is.

17   And then there are maintenance requirements that,

18   similar to Hertz we make them put them on the

19   plan. So that gives you some bite.

20            MR. ROTHFEDER:         But if that’s our

21   building code, I mean?

22            MR. LAPINE:        Yeah. Well, no, it’s a

23   state building code, state building code

24   requirement for how you size these.



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 37 Original page ↗

                                                            Page 37
1    February 3, 2026

 2            MR. KESSLER:        Right.

 3            MR. LAPINE:        And then the maintenance

 4   requirements, you could require them to place

 5   these on the plan so that it gives you the bite

 6   in the event you want to make sure that they’re

 7   being constantly maintained. So you can go and

 8   you could check on them by having those

 9   maintenance requirements on the plans.

10            MR. KESSLER:        Okay. But that doesn’t

11   happen routinely?

12            MR. LAPINE:        I can’t answer it to DOTS.

13            MR. KESSLER:        I mean, once they’re

14   developed according to, rules, regulations,

15   whatever --

16            MR. ROTHFEDER:         Right.

17            MR. KESSLER:        -- after that, anything,

18   anything goes.

19            MR. KEHOE:       We’ll get you an answer.

20            MS. BROSNAN:        I’ll get you a more

21   thorough answer from the code.

22            MR. ROTHFEDER:         And it’d be good if we

23   could put something in the resolution.

24            MR. KESSLER:        Any, any, Tom?



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 38 Original page ↗

                                                              Page 38
1    February 3, 2026

 2              MR. BIANCHI:        Under the previous

 3   application for this facility, I remember that

 4   there was a lot of discussion about the traffic

 5   flow, especially in the northbound traffic flow.

 6   And this is, we’re talking cars at that time and

 7   how they would access this facility. Now we’re

 8   talking about trucks. So could you describe how

 9   that’s, how northbound, I guess it’s northbound.

10   Yeah, northbound traffic will access this

11   facility? Do they have to go to the intersection

12   further north and then turn around and come back

13   down?

14              MR. GILCHRIST:         No. And the driveway

15   that’s there was designed to accommodate trucks

16   and it was approved by the DOT, and, you know,

17   rigorously studied. There’s, there was a

18   requirement, we’re allowed left turns in, and

19   there’s a requirement that it would be revisited

20   to see how it’s working. So, as part of the car

21   wash approval, left turns into our driveway and

22   right turns out only.

23              MR. BIANCHI:        There’ll be a left turn

24   allowed in going north?



                         Geneva Worldwide, Inc.
             228 Park Ave S - PMB 27669. New York, NY 10003

Page 39 Original page ↗

                                                              Page 39
1    February 3, 2026

 2              MR. GILCHRIST:         From the northbound,

 3   yes.

 4              MR. BIANCHI:        Into the facility?

 5              MR. GILCHRIST:         Yes.

 6              MR. BIANCHI:        And you said, what did DOT

 7   say about that?

 8              MR. GILCHRIST:         I have, there’s a note

 9   right on my drawing.

10              MR. BIANCHI:        Did they approve that or

11   did they --

12              MR. KEHOE:       Well, there’s a prohibition

13   right now for no left turn in the morning rush

14   hour, and on weekends, in the afternoon and

15   there’s -- weekdays. And there’s signage supposed

16   to be put Out there.

17              MR. KESSLER:        That was with the car

18   wash.

19              MR. KEHOE:       That was with the car wash.

20   But as they said, they’re going to retain John

21   Canning and we’ll have our own traffic person --

22              MR. KESSLER:        Okay.

23              MR. KEHOE:       -- to see if that changes.

24              MR. BIANCHI:        Okay. That’s, that’s what



                         Geneva Worldwide, Inc.
             228 Park Ave S - PMB 27669. New York, NY 10003

Page 40 Original page ↗

                                                            Page 40
1    February 3, 2026

 2   I was getting to, just to review that again.

 3   Because now we’re talking trucks versus cars, and

 4   that was my concern.

 5            MR. GILCHRIST:         Yeah. So the, the notes

 6   on the drawing, as, as Chris says, no, left turn

 7   7:00 a.m. to 9:00 a.m., 4:00 p.m. to 6:00 p.m.

 8   weekdays, if safety or operational issues arise,

 9   the time restriction on northbound left turn

10   entering may be removed and all left turns

11   prohibited.

12            MR. BIANCHI:        Okay.

13            MR. GILCHRIST:         So that was, that was

14   language on the drawing that was required.

15            MR. BIANCHI:        But that was on the

16   previous application.

17            MR. GILCHRIST:         Yes.

18            MR. BIANCHI:        Not this one.

19            MR. GILCHRIST:         With the car wash at a

20   hundred, over a hundred cars a day.

21            MR. BIANCHI:        Right. But again, they

22   were cars, not trucks. But you’re saying 14

23   trucks in and out of the shop per month.

24            MR. GILCHRIST:         That, that’s right. And



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 41 Original page ↗

                                                              Page 41
1    February 3, 2026

 2   six employees coming in and going per day.

 3              MR. LAPINE:        We want to make sure that

 4   they can accommodate whatever the trailer that’s

 5   delivering.

 6              MR. SCHWARTZ:         [unintelligible]

 7   [00:32:33] deliveries, like the first one is at

 8   5:00 in the morning, so as you’ll see, and it’s

 9   in the narrative that we submitted, and it’ll be

10   in John’s report also. It’s not even during the

11   peak times, the traditional peak times, like the

12   first delivery at 5:00 a.m., the next one goes

13   out, comes in, I think at 11:00 a.m. So it’s not

14   the traditional peak periods.

15              MR. KESSLER:        Okay.

16              MR. BIANCHI:        I’d like to see maybe John

17   Canning can appear at the next meeting, at our

18   next meeting just to discuss that a little bit

19   more and review what the DOT’s take is on it, now

20   that we’re talking about trucks, We’ll have him

21   here.

22              MS. BROSNAN:        What is the maximum size

23   truck that you anticipate for deliveries?

24              MR. GILCHRIST:         Thirty. No trailers.



                         Geneva Worldwide, Inc.
             228 Park Ave S - PMB 27669. New York, NY 10003

Page 42 Original page ↗

                                                            Page 42
1    February 3, 2026

 2               MS. BROSNAN:     Thirty feet, no trailers?

 3               MR. GILCHRIST:      No trailers. You know,

 4   it’s --

 5               MR. ROTHFEDER:      So it’s a box truck?

 6               MR. GILCHRIST:      Well --

 7               MR. SCHWARTZ:      Sprint trucks, like --

 8               MR. GILCHRIST:      Tractors for tractor

 9   trailers, cement trucks, any kind of big, big

10   trucks.

11               MS. BROSNAN:     What, what side of the

12   building do you anticipate delivery?

13               MR. GILCHRIST:      Excuse me?

14               MS. BROSNAN:     What side of the building

15   do you anticipate delivery.

16               MR. GILCHRIST:      You know, delivery.

17               MS. BROSNAN:     Do they offload behind the

18   building?

19               MR. GILCHRIST:      Yes.

20               MS. BROSNAN:     Okay.

21               MR. KESSLER:     So your bays can

22   accommodate a 30 foot truck is what you’re

23   saying?

24               MR. GILCHRIST:      Yes.



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 43 Original page ↗

                                                               Page 43
1    February 3, 2026

 2               MR. KESSLER:        Okay.

 3               MR. SCHWARTZ:         Many of the trucks will

 4   be smaller and that’s all in the project

 5   narrative that we submitted.

 6               MR. GILCHRIST:         Right. The largest would

 7   be 30.

 8               MR. KESSLER:        Okay. Any, any other

 9   comments from the board, staff? Yeah, sure.

10               MR. MCKINLEY:         Would there ever be a

11   time when some of these trucks or parts or frames

12   would be, sorry, frames would be in, in storage

13   behind? Or is everything contained inside the

14   building? Like all the repair work is done inside

15   the building?

16               MR. GILCHRIST:         All the, all the repair

17   work is done inside, yes.

18               MR. MCKINLEY:         Okay. So it’s not a

19   salvage or --

20               MR. GILCHRIST:         No.

21               MR. SCHWARTZ:         Not stockpiling, no.

22               MR. GILCHRIST:         No.

23               MR. MCKINLEY:         That’s my question. Okay.

24               MR. SCHWARTZ:         No.



                          Geneva Worldwide, Inc.
              228 Park Ave S - PMB 27669. New York, NY 10003

Page 44 Original page ↗

                                                            Page 44
1    February 3, 2026

 2            MR. MCKINLEY:         Great.

 3            MR. KESSLER:        Anything else?

 4            MR. SCHWARTZ:         Mr. Chairman, if I could

 5   just procedurally before you conclude?

 6            MR. KESSLER:        Sure.

 7            MR. SCHWARTZ:         If there’s no other

 8   substantive comments tonight, and we’ll have Mr.

 9   Canning here next time and we’ll respond

10   obviously to any comments we can get back from

11   staff. If your board would, please just declare

12   your intent to serve as lead agency tonight, at

13   least start that process, that would be

14   appreciated.

15            MR. KESSLER:        Okay. We’ll add that to

16   the, to the motion. So, who has this? Peter?

17            MR. MCKINLEY:         I do. Okay. Mr. Chairman,

18   I’d like to refer this back to staff for further

19   discussion and in addition, we’d like to, declare

20   that the planning board would be lead agent for

21   PB 2025-18 for Roa Hook Realty, LLC, site

22   development.

23            MR. KESSLER:        Thanks. Second, please.

24            MR. KOBASA:        Second.



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 45 Original page ↗

                                                            Page 45
1    February 3, 2026

 2              MR. KESSLER:      On the question.

 3              MR. CUNNINGHAM:        It just, we’re

 4   circulating for now the notice to be lead agency

 5   and then at the next meeting likely be able to

 6   declare lead agent.

 7              MR. KEHOE:     Yeah. So technically you’re

 8   only declaring your intent to make sure no one

 9   objects.

10              MR. KESSLER:      Right.

11              MR. KEHOE:     And then at a later meeting,

12   you’ll actually declare yourself lead agency.

13              MR. CUNNINGHAM:        Actually you’ll

14   probably to wait until April because it’s not 30

15   days given that February’s a short month, so

16   it’ll probably be in April meeting you could

17   actually declare lead agency.

18              MR. KESSLER:      Thank you. All right,

19   we’re on the question. All in favor?

20              MULTIPLE:     Aye.

21              MR. KESSLER:      Opposed? Okay. Thank you.

22              MR. SCHWARTZ:        Good night. Thank you.

23              MR. KESSLER:      Okay. Moving on, the

24   second item under old business, it’s the



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 46 Original page ↗

                                                            Page 46
1    February 3, 2026

 2   application of Dakota Recycling Service, LLC and

 3   Dakota Concrete Services, LLC for the property of

 4   Briga Enterprises Incorporated, and Bilotta

 5   Realty of Westchester, Incorporated for amended

 6   site plan approval for the existing Dakota

 7   Recycling Services and Dakota Concrete Services

 8   for property located at 2099 Albany Post Road,

 9   drawings dated January 20, 2026. Mr. Steinmetz,

10   good evening again.

11            MR. STEINMETZ:         Good evening, Mr.

12   Chairman, members of the board, I’m here this

13   evening also on behalf of Bilotta and Dakota and

14   Briga. As we indicated briefly at the work

15   session, as you heard from Chris, we are not

16   planning on making any kind of comprehensive

17   presentation. I do believe Peter Loyola from CLA

18   engineering should be on if the board has any

19   specific questions. We thought, and I don’t want

20   to speak for Chris, but Chris reached out and

21   indicated that there might be a benefit to just

22   appearing before your board to let you know that

23   although this application was filed last summer,

24   there has been quite a bit of work going on



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 47 Original page ↗

                                                            Page 47
1    February 3, 2026

 2   between staff and our technical consultants. They

 3   are addressing a number of issues between them.

 4   We expect to hopefully have most of those issues

 5   answered and be back before you at the next

 6   meeting.

 7              I did want to address just briefly

 8   something that I heard come up at the work

 9   session, so that you don’t leave tonight with any

10   kind of misimpression. It is our understanding,

11   both my client and my firm, that the uses on this

12   property are not an issue and have not been an

13   issue, and then have not been raised by staff and

14   your outside consultants as an issue.

15              As Mr. Lapine, prompted you with his

16   question during the work session, there, there

17   have been some technical questions raised by DOTS

18   and Chris about whether the areas on the site

19   have possibly moved to some extent. Although, I

20   think Mr. Bilotta feels that that’s not accurate.

21              In terms of the uses, as you indicated,

22   Mr. Chairman, this board did grant approval over

23   20 years ago. This is a lawful concrete plant as

24   well as a recycling facility and contractor’s



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 48 Original page ↗

                                                              Page 48
1    February 3, 2026

 2   yard. And as you heard me say, probably at the

 3   beginning of 2025, at some meetings, there have

 4   been numerous litigations commenced against the

5    town, specifically against the planning board by

6    a neighboring property owner. And in each of

7    those litigations, the town, I believe, took the

8    position that the use was lawful and was

 9   permitted.

10              So the reason that we’re here, in my

11   opinion on the back of the property, is that,

12   taking a step back with you, we had filed an

13   application to construct a metal butler building

14   for storage on what I consider the front of the

15   property, along Albany Post Road. That prompted a

16   number of questions during our deliberation,

17   during your deliberations and our discussion of

18   that.

19              And we were asked by DOTS and staff to

20   examine the back of the property, in particular

21   with regard to SWIPP and storm water, storm water

22   management. So during the processing of what was

23   a modest storage building at the front of the

24   property, we sort of walked into the notion of



                         Geneva Worldwide, Inc.
             228 Park Ave S - PMB 27669. New York, NY 10003

Page 49 Original page ↗

                                                            Page 49
1    February 3, 2026

 2   making sure that your board had a good clean

 3   record of the back of the property and the storm

 4   water management that was occurring there.

 5            Unfortunately, over a year ago, I guess

 6   it’s now over a year ago, there was then a fire

 7   that on the property and that kind of got in the

 8   way and delayed some things and at least raised a

 9   number of issues for the building department that

10   had to be answered.

11            So long and short, Bilotta, Dakota,

12   they’re operating, they’ve been operating for

13   over 25 years, or 20 plus years. They believe

14   they’ve been operating lawfully. It’s a pretty

15   critical industry and business here in your

16   community in terms of recycling asphalt and rock

17   used in construction jobs, including on Route 9

18   quite regularly. So, long story short, I hope

19   that staff is getting the information it needs

20   from Peter Loyola and, and staff and our

21   technical team. We look forward to continuing to

22   work with DOTS.

23            But I did not want your board to leave

24   tonight thinking we had tacitly acknowledged the



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 50 Original page ↗

                                                               Page 50
1    February 3, 2026

 2   chairman’s comment about uses, because we, we

 3   actually quite vehemently disagree. The uses are

 4   lawful. You’ve permitted them. They’ve operated

 5   for over 20 years. We’re trying to clean up some

 6   technical issues and leave you with a good site

 7   that has a good clean site plan.

 8               MR. KESSLER:        Any comments from the

 9   board?

10               MR. CANTRELL:         I think it, I think it

11   would be good to understand what the existing

12   permit outlines and what’s allowed and make sure

13   that you all are in compliance with that. I think

14   it would be good to hear from staff on that to

15   see what they think of it. And then, you know,

16   just some questions about the detention pond

17   outlets and so forth, so.

18               MR. STEINMETZ:         Okay. Understood.

19               MR. CANTRELL:         Thank you.

20               MR. KOBASA:        I’m just      going to bring up

21   the drainage that’s along the access easement,

22   the road that the concrete trucks used to get to

23   the plant, that I raised while we were out there,

24   just to make sure that that’s addressed, the idea



                          Geneva Worldwide, Inc.
              228 Park Ave S - PMB 27669. New York, NY 10003

Page 51 Original page ↗

                                                            Page 51
1    February 3, 2026

 2   that water was not making it into the drains, as

 3   we could see when we were out there.

 4              MR. STEINMETZ:       So, Peter Loyola is on

 5   screen, and Kevin, unless you want an answer

 6   tonight, I’m going to ask, I’m going to ask --

 7              MR. KOBASA:      I don’t need an answer

 8   tonight.

 9              MR. STEINMETZ:       I figured that.

10              MR. KOBASA:      I just want to make sure.

11              MR. STEINMETZ:       I’m going to ask Peter

12   and CLA to respond to both your comments and,

13   and, and Kellan’s question as well.

14              MR. KOBASA:      Okay.

15              MR. MCKINLEY:       I was just, I would like

16   to just go on the record. So I did attend the

17   site visit and, I was pleasantly surprised to see

18   it was a well run operation, excuse me. It was an

19   operation. It had some rigor to it. So when we

20   walked through, it wasn’t haphazard. It didn’t

21   look like it was strung together. I don’t know

22   much about the construction industry, but I do

23   want to say that I was pleasantly surprised to

24   see that there was a logic to it and there was



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 52 Original page ↗

                                                             Page 52
1    February 3, 2026

2    discussion about the recycling and the benefits

 3   of that. So I do want to say that. But, to

 4   Kevin’s point, there was some considerable water

 5   that was moving down that kind of didn’t look

 6   like it was being addressed, or excuse me, it was

 7   out of, out of bounds, in the roadway.

 8             MR. STEINMETZ:         So, Peter, we will make

 9   sure we answer the technical question and I

10   appreciate you stating for the record what you

11   did.

12             MR. CANTRELL:         I just have one more

13   question that, do you, do you have a DEC permit

14   to operate?

15             MR. STEINMETZ:         Yeah, there’s a, a part

16   360 registration as I understand it. I think,

17   Chris, am I right about that?

18             MR. LAPINE:        You’re correct.

19             MR. STEINMETZ:         Yeah.

20             MR. CANTRELL:         And do they do

21   inspections to ensure that you’re in compliance?

22             MR. STEINMETZ:         As I’m sure you know,

23   Kallen, based upon your professional expertise,

24   the DEC and Region Three come out periodically



                        Geneva Worldwide, Inc.
            228 Park Ave S - PMB 27669. New York, NY 10003

Page 53 Original page ↗

                                                            Page 53
1    February 3, 2026

 2   and conduct inspections? There are part 360

 3   inspectors that go out, and do those little forms

 4   that you probably know better than I do, where

 5   they check the boxes on compliance, so yes.

 6            MR. CANTRELL:         Okay. I often drive by

 7   the, on Albany Post, and there’s, a lot of times

 8   there’s debris in the roadway from the plant. And

 9   I don’t know if, you know, if there’s any, any

10   way to prevent that in the future from coming,

11   because it’s across the street from the VA there.

12   You know, and I worry that, you know, the wrong

13   kind of debris will be in the roadway. So it’s

14   just something that --

15            MR. STEINMETZ:         Total, I -- obviously

16   that can be a condition of approval. But one of

17   the things, and, and you all can help me because

18   you know, the geography better than I. My

19   understanding is board members went out during

20   the site inspection and were surprised that stuff

21   that they thought was Bilotta Dakota was actually

22   Peckham. Am I correct about that?

23            MR. MCKINLEY:         Which one’s Peckham?

24            MR. BIANCHI:        The house next to it?



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 54 Original page ↗

                                                            Page 54
1    February 3, 2026

 2            MR. KESSLER:        Peckham is down by the

 3   railroad, right?

 4            MR. BIANCHI:        Yeah.

 5            MR. STEINMETZ:         Correct. And people

 6   thought that was all part of this. So I, so I

 7   don’t know what debris you’re talking about. I

 8   just, I know that, that I’ve heard more than once

 9   that everybody kind of thought, well, there’s

10   this, all this industrial stuff. It’s all one

11   operation. It’s not, there, so I, I can’t tell

12   you what you observed and, but I absolutely

13   believe you have a right to impose conditions

14   that, nothing drifts off the site.

15            MR. CANTRELL:         I just wanted to

16   understand if that’s, that’s something that

17   anyone else has seen, or if, you know, any of the

18   other board members witnessed that.

19            MR. KEHOE:       Meaning drainage or like

20   aggregate?

21            MR. CANTRELL:         No, it’s aggregate.

22            MR. KOBASA:        I think it’s the dust on

23   the aggregate that you can see.

24            MR. CANTRELL:         It’s on Albany Post --



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 55 Original page ↗

                                                             Page 55
1    February 3, 2026

 2              MR. KOBASA:       When you --

 3              MS. LAVARNWAY:        Okay, So that’s not

 4   Peckham.

 5              MR. CANTRELL:        When it immediately comes

 6   out?

 7              MR. KOBASA:       No, it’s when you come out

 8   of the train station, if you come out there and

 9   make the left right at that intersection, you can

10   see a lot of dust, construction, like concrete

11   cement, like, I mean, I don’t want to say it’s

12   [unintelligible] [00:44:06] so that it would form

13   a cement, but, you know, the refines and

14   everything from all of that --

15              MR. CUNNINGHAM:         Got it.

16              MR. KOBASA:       -- drifts down there,

17   whether it’s on the trucks when it comes and

18   settles, but mine is the, it’s not Peckham, it’s

19   the stuff that I’m concerned about starts from up

20   there and goes down through the Peckham site.

21              MR. STEINMETZ:        I appreciate The

22   Clarification. Again, Peter, who’s listening, I

23   will ask Peter to take a look at that and make

24   sure we address that in our next submission.



                        Geneva Worldwide, Inc.
            228 Park Ave S - PMB 27669. New York, NY 10003

Page 56 Original page ↗

                                                            Page 56
1    February 3, 2026

 2            MR. KESSLER:        So the question is, is it

 3   the trucks going in or is it trucks coming out?

 4            MR. KOBASA:        My guess it’s the trucks

5    coming out, would be my assumption.

6             MR. KESSLER:        Any other comments?

 7            MR. KEHOE:       Uh -- oh, sorry, go ahead.

 8            MR. KESSLER:        Go ahead.

 9            MR. KEHOE:       No, just I’ll say something

10   on the question.

11            MR. KESSLER:        Okay. So, we’ll be, as we

12   said, referring this back. So, Mr. Bianchi?

13            MR. BIANCHI:        Mr. Chairman, I move that

14   we declare our intent to be lead agent and to

15   refer this back to staff for continued review.

16            MR. KESSLER:        Second, please.

17            MR. ROTHFEDER:         Second.

18            MR. KESSLER:        And on the question?

19            MR. BIANCHI:        Tom took care of it.

20            MR. KESSLER:        Oh, he did?

21            MR. KEHOE:       Yeah.

22            MR. KESSLER:        I see. All in favor?

23            MULTIPLE:       Aye.

24            MR. KESSLER:        Opposed?



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 57 Original page ↗

                                                            Page 57
1    February 3, 2026

 2            MR. STEINMETZ:         Thank you.

 3            MR. KESSLER:        Thank you. Okay. Moving on

 4   to new business this evening, two items, the

 5   first one is the application of Oregon Homes for

 6   preliminary plat approval and for steep slope and

 7   tree removal permits for a proposed seven-lot

 8   major subdivision for six residential lots and

 9   one mixed use parcel for property located at 1127

10   Oregon Road and 2 Red Mill Road, drawings dated

11   November 5, 2025. Good evening.

12            MR. JOSEPH RIINA:          Good Evening. Joseph

13   Riina, principal site design consultant

14   representing Oregon Homes, Inc. With me tonight

15   are the owners and sponsors of the project, John

16   Gerbino, Mike Mazzola, and Mike Lowe. Also with

17   me, is, Allison Marino from my office, one of my

18   engineers.

19            The parcel as, Chris had explained, is

20   at the intersection of Oregon Road and Red Mill.

21   And I apologize that the, the roads are not

22   labeled on the plan. We’ll get that on there.

23   But, the road at the bottom of the sheet is

24   Oregon, and to the right of the site is Red Mill.



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 58 Original page ↗

                                                            Page 58
1    February 3, 2026

 2   So altogether there are two parcels there. The

 3   smaller of the parcels is right on the corner.

 4   And, that’s, that’s just under, that’s 0.4 acres,

 5   just under a half acre. And the larger parcel is

 6   just over two acres altogether, it’s 2.4 acres,

 7   2.48 acres, sorry. The site is zoned CC,

 8   community commercial and, what we’re proposing is

 9   permitted in this zone.

10             So, currently, this is, as explained,

11   this is currently the Carvel site. There are the

12   remains of a driveway and two curb cuts that

13   connect both roads. And you could see it there,

14   it kind of loops across the front of the, across

15   the corner there. And, about a third of the site

16   is open and clear, and the remainder of the site

17   is lightly wooded. On the left side of the

18   property, running parallel to that property line,

19   we have a 60-foot, deeded restriction or a buffer

20   zone that we cannot clear or, do any development

21   within.

22             So, the proposal has two aspects to it.

23   One is the smaller, corner piece. We are going to

24   go with a mixed use on that, which would be



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 59 Original page ↗

                                                            Page 59
1    February 3, 2026

 2   retail, a 2,600 square foot retail space with two

 3   residential apartments above. The larger parcel,

 4   we’re looking to subdivide into six single family

 5   residential lots. The, as you could see, we’re

 6   proposing a roadway coming in off of Red Mill,

 7   terminating in a cul-de-sac and each of the lots

 8   coming off of that. Again, we’re respecting that

 9   60-foot buffer on the, on the, left side of the

10   property there.

11            The lots all comply to the zoning

12   standards. We have, we’re demonstrating

13   sufficient parking on the commercial site, and

14   we’ve provided two different concepts for the

15   residential site and, you know, get to give you a

16   different look and based on some suggestions also

17   from the staff. And at this time, we’re want to

18   give you a first look at this and get some

19   impressions, if you have any impressions or any

20   comments. And we’re really looking to move in a

21   direction with the residential concept, so we

22   were hoping we could flush a little bit of that

23   out tonight.

24            And, we also hear staff’s comment about



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 60 Original page ↗

                                                            Page 60
1    February 3, 2026

 2   having two separate curb cuts, one for the

 3   commercial and one for the road servicing the

 4   residential site. And the owners of the property

 5   have no objection to eliminating the one curb cut

 6   and having it, having just the single curb cut

 7   for the main roadway and coming off of that to

 8   access the commercial site.

 9            MR. KESSLER:        Will that affect the

10   parking for the commercial at all?

11            MR. RIINA:       We’ll have to, we’ll have to

12   lay that out and, and see that, but we’re

13   definitely open to doing that.

14            MR. KESSLER:        I haven’t seen this in a

15   while. What, what is the, lot area for CC, what’s

16   the requirement?

17            MR. KEHOE:       7,500.

18            MS. LAVARNWAY:         7,500.

19            MR. KEHOE:       About 7,500?

20            MR. RIINA:       It’s, it’s on the, should be

21   on the zoning table there.

22            MS. LAVARNWAY:         I think it’s 7,500.

23            MR. KEHOE:       Yeah, 7,500.

24            MR. KESSLER:        Oh, there it is, 7,500,



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 61 Original page ↗

                                                              Page 61
1    February 3, 2026

 2   thank you. 7,500.

 3              MR. KEHOE:       And I don’t know how much

 4   you’ve focused on the difference between one and

 5   two, but I don’t think a planning staff is much

 6   of a fan of number two.

 7              MR. KESSLER:        Yeah, I agree with you.

 8              MR. KEHOE:       Okay.

 9              MR. KESSLER:        So I mean, obviously we’ll

10   refer this back, they’ll do a review memorandum.

11              MR. RIINA:       Yep, mm-hmm.

12              MR. KESSLER:        You know, I, certainly

13   we’ll have to have fire look at this with the

14   cul-de-sac as well.

15              MR. KEHOE:       Yeah. And, and then one

16   thing is, I, you know, you’ve got time, but I

17   think the elevations of the proposed mixed use

18   building will be very important to the

19   neighborhood out there, what it’s                going to look

20   like.

21              MR. RIINA:       Yeah, of course, yeah.

22              MR. MCKINLEY:         I’m, I’m familiar with

23   the, the area, but do more people use Oregon Road

24   or do people just go up to the town of Cortlandt?



                         Geneva Worldwide, Inc.
             228 Park Ave S - PMB 27669. New York, NY 10003

Page 62 Original page ↗

                                                            Page 62
1    February 3, 2026

 2   Is that a heavily trafficked roundabout position

 3   in the street?

 4               MR. KOBASA:     I would say Red Mill is

 5   kind of a cut through.

 6               MS. BRASNON:     Oh yeah.

 7               MR. KEHOE:     It’s busy.

 8               MR. KOBASA:     That’s a cut through from

 9   strawberry.

10               MR. KESSLER:     And undersized.

11               MR. KOBASA:     Yeah.

12               MR. MCKINLEY:      So it’s not just

13   bypassed?

14               MR. KESSLER:     Right.

15               MR. KEHOE:     Right. And then, you know,

16   it’s a mountable roundabout, you know, so you can

17   sort of, you know, but it, it’s a busy, active

18   location.

19               MR. RIINA:     Yeah, sure.

20               MR. KOBASA:     It’s busy all day.

21               MS. HILDINGER:      It’s always busy.

22               MR. BIANCHI:     At the appropriate time,

23   maybe a site visit is something you want to

24   consider.



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 63 Original page ↗

                                                            Page 63
1    February 3, 2026

 2            MR. KESSLER:        Yeah. We’ll wait for the

 3   review memorandum, but yes. So any other

 4   comments? So I think clearly one’s better than

 5   two, in terms of your two proposals --

 6            MR. RIINA:       Two or --

 7            MR. KESSLER:        -- but there’s still work

 8   to be done on one I’m sure.

 9            MR. KEHOE:       We don’t really like that

10   sort of flag lot in back.

11            MR. RIINA:       One?

12            MR. KESSLER:        Yeah.

13            MR. KESSLER:        Yeah. Your first plan,

14   yeah, as compared to two.

15            MR. RIINA:       Okay.

16            MR. KESSLER:        And, yeah, I think door

17   number one. But, there’ll be more review and --

18            MR. RIINA:       Of course.

19            MR. KESSLER:        There’ll be more detailed

20   discussion, I’m sure about the placement of the

21   houses, as you propose them. So, if there’s no

22   other comments, then, Jeff?

23            MR. ROTHFEDER:          I move that we declare

24   the planning board’s intent to be lead agent and



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 64 Original page ↗

                                                            Page 64
1    February 3, 2026

 2   refer the application back to staff.

 3               MR. KESSLER:     Thank you. Second, please.

 4               MR. BIANCHI:     Second.

 5               MS. HILDINGER:      Second.

 6               MR. KESSLER:     And on the question, all

 7   in favor?

 8               MULTIPLE:    Aye.

 9               MR. KESSLER:     Opposed?

10               MR. RIINA:     Thanks very much.

11               MR. KESSLER:     Thank You.

12               MR. RIINA:     Okay, goodnight.

13               MR. KESSLER:     Final item this evening,

14   it’s, new business, the application of VS

15   Construction for site development plan approval

16   and for steep slope and tree removal permits for

17   a proposed 9,600 square foot commercial building

18   located on future parcel three within the medical

19   oriented district for a property located at 2003

20   Crompond Road, drawings dated January 21, 2026.

21               MR. STEINMETZ:      Good evening.

22               MR. KESSLER:     Hello again.

23               MR. STEINMETZ:      Mr. Chairman, members of

24   the board, we are ex extremely pleased to be here



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 65 Original page ↗

                                                            Page 65
1    February 3, 2026

 2   tonight in connection with the kickoff of this

 3   particular future lot within the proposed

 4   subdivision. This parcel alongside Lafayette was

 5   studied during the MOD review. It was always

 6   contemplated to be the commercial potential

 7   property. The town spent, a great, the town board

 8   spent a great deal of time determining what they

 9   wanted to see on this particular parcel.

10            And we are here tonight with a 9,600

11   square foot commercial building and the concept

12   would be for this to be a pharmacy or medical

13   retail, medical supply type operation. There is a

14   lovely building that has been designed by Sal

15   Coco and his office. Matt Steinberg is going to

16   walk us through the site plan. What we have

17   before you tonight is the beginning or initiation

18   of a site plan review to the extent that you need

19   to, and Michael and Chris, I don’t even know

20   whether they are doing a lead agency --

21            MR. CUNNINGHAM:          No.

22            MR. STEINMETZ: -- or not. No, I didn’t

23   think so, as I started to say it. So really this

24   is, this is legitimately a pure planning and



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 66 Original page ↗

                                                            Page 66
1    February 3, 2026

 2   engineering exercise. We have filed our

 3   materials. We’re going to be working with staff

 4   to look at the retaining wall, the setbacks.

 5   Obviously, as you mentioned in the work session,

 6   the one gentleman who spoke at last month’s

 7   public hearing with regard to the Benchmark

 8   Assisted Living really was talking about this

 9   parcel, and as you mentioned, at the work

10   session, his, irrigation well.

11            I will defer to the technical folks, but

12   as one or more of you indicated at the work

13   session, that particular property is on municipal

14   water so there is no, adverse impact to that

15   property in terms of potable water supply,

16   irrigation water supply or otherwise.

17            And again, this site and this use was

18   specifically approved during, or analyzed and

19   ultimately determined to not have a significant

20   adverse environmental impact, during the SEQRA

21   process. So with that --

22            MR. KESSLER:        Wait, just one question.

23   You said, so it’s a, a pharmacy and a what, a

24   medical office use?



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 67 Original page ↗

                                                            Page 67
1    February 3, 2026

 2              MR. STEINMETZ:       Medical Supply, medical

 3   supply.

 4              MR. KESSLER:      Oh, supply, you said

 5   medical office use.

 6              MR. STEINMETZ:       I said medical supply or

 7   retail, medical retail.

 8              MR. KESSLER:      Like a DME kind of place

 9   or a --

10              MR. STEINMETZ:       Well, I don’t --

11              MR. KESSLER:      Like medical equipment,

12   durable --

13              MR. STEINMETZ:       Medical equipment,

14   walkers, wheelchairs.

15              MR. KESSLER:      It’s DME, the term is DME.

16              MR. STEINMETZ:       Thank you for the

17   acronym, What does it stand for, Mr. Chairman,

18   just so we all get educated?

19              MR. KESSLER:      Durable medical equipment.

20              MR. STEINMETZ:       Okay. Thank you. So,

21   with, with that, there, there is nothing like

22   that in the town currently that we’re aware of,

23   medical.

24              MR. KESSLER:      I thought there was one up



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 68 Original page ↗

                                                              Page 68
1    February 3, 2026

 2   by King Buffet.

 3              MR. BIANCHI:        Yeah.

4               MR. STEINMETZ:         Medical Equipment?

 5              MR. BIANCHI:        Yeah, there is.

 6              MR. STEINMETZ:         Okay. Well, there may be

 7   another one.

 8              MR. KESSLER:        Medical supply. I got

 9   crutches there once, I remember.

10              MR. STEINMETZ:         Oh, is that right?

11   Interesting. We’ll let Matt talk about the site

12   plan.

13              MR. STEINBERG:         Thank you. Matt

14   Steinberg, DTS Provident. So the parcel, which we

15   call parcel three as part of the Evergreen Manor

16   site, it’s at the northwest corner of the site.

17   It’s at the intersection of Crompond and

18   Lafayette. It’s right on that corner. The future

19   subdivided lot will be approximately two acres in

20   size and that includes an access drive that goes

21   back out to the, the main Evergreen Manor

22   roadway. The access out to Lafayette is emergency

23   only, so it wouldn’t be open to the, to the

24   general public. It’d be a gated access.



                         Geneva Worldwide, Inc.
             228 Park Ave S - PMB 27669. New York, NY 10003

Page 69 Original page ↗

                                                            Page 69
1    February 3, 2026

 2             The topography, so at the top of this

 3   plan, we created a section which we can provide,

 4   to the board. It shows the existing topography,

 5   so Crompond Road is about, approximately

 6   Elevation 360, it kind of changes along the

 7   frontage and rise, the property rises from there,

 8   back to elevation 390 at the rear of the parcel.

 9             So the proposed project would set the

10   parking lot and building at approximately

11   elevation 370, so it’ll create a building pad.

12   And the building is proposed to set into the

13   hillside essentially, become part of the

14   retaining wall system.

15             So just to clarify, so the building is

16   approximately 9,600 square feet. So it’s been

17   designed as 8,000 square feet for the pharmacy

18   and another 1,600 square feet for a medical

19   office.

20             MR. KESSLER:       Why?

21             MR. STEINBERG:        We’ve designed it so

22   that the, it would meet the medical office --

23             MR. KESSLER:       Medical supply?

24             MR. STEINBERG:        No, general medical



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 70 Original page ↗

                                                               Page 70
1    February 3, 2026

 2   office under the code.

 3               MR. KESSLER:        That’s not what David just

 4   said.

 5               MR. KEHOE:       So, no, so the 8,000 is

 6   either a pharmacy --

 7               MR. STEINBERG:         Yes.

 8               MR. KEHOE:       -- or a medical equipment

 9   sales. They haven’t settled on that yet.

10               MR. KESSLER:        Right. So what’s the

11   1,600?

12               MR. STEINBERG:         The 1,600 is the, yeah,

13   1,600 is medical office space. So a --

14               MR. KEHOE:       A doctor office.

15               MR. STEINBERG:         -- a physician’s office.

16               MR. KESSLER:        Okay. Like, like what

17   exists across, on the Gyrodyne site?

18               MR. STEINBERG:         Right, but obviously, at

19   a much smaller scale. So the parking, there’s 43

20   at grade parking spaces that accommodates both

21   uses based on the requirements of the MOD zoning.

22   So it’s 32 for the pharmacy, and another 11 for

23   the medical office, so a total of 43. So during,

24   during the SEQRA review, this building,



                          Geneva Worldwide, Inc.
              228 Park Ave S - PMB 27669. New York, NY 10003

Page 71 Original page ↗

                                                            Page 71
1    February 3, 2026

 2   essentially it’s, the overall building envelope

 3   and parking is very similar to what was studied

 4   during the SEQRA review, but at that time, the

 5   building was pulled closer to the front, and the

 6   parking was also on the side, but around the rear

 7   of it. During that process, there were a number

 8   of uses that were contemplated during the MOD.

 9            Ultimately, the town board adopted a

10   code that really only allowed for the medical

11   use. So in, you know, looking at the site plan,

12   and we met with staff, it made sense to try to

13   push it to the back, so that the building could

14   act partly as the retaining system into the

15   hillside and to have parking along, essentially

16   the front and side of the building. Part of this

17   is also due to just the topographic change and

18   what kind of the circumstances that changed,

19   during that overall, MOD review.

20            The site has a 30, so, if you remember

21   the, the east side of the site has a hundred foot

22   non-disturbance buffer. This side of the site has

23   a 30-foot version of that. So the, the idea is to

24   place that retaining wall at the 30-foot mark and



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 72 Original page ↗

                                                            Page 72
1    February 3, 2026

 2   then there’s a number of, it’s a wooded area

 3   behind. There’d be additional planting and

 4   screening added to supplement that at the top,

 5   above that wall.

 6            Heather, if you could go to the last

 7   slide. And there’s a conceptual landscape plan in

 8   the set that we had submitted. So there’s,

 9   there’s existing wooded area along the front,

10   along Crompond Road, which we would try to

11   maintain as much as we can and then supplement

12   around the parking lot. The architecture has been

13   designed, as it’s essentially a retail

14   storefront, a mix of light colored brick and

15   hardy siding. There’d be the storefront opening

16   for the pharmacy and then obviously for the

17   medical office, you know, the entry, their entry

18   lobby essentially.

19            And then, you know, we’ll be continuing

20   to study this further. There’s obviously tree

21   removal, steep slopes, wetlands that we will

22   continue to study. But we had met, had a pre-

23   application with staff and they suggested that

24   we, you know, we had enough at this time to



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 73 Original page ↗

                                                              Page 73
1    February 3, 2026

 2   obviously present it to the board to get the

 3   initial feedback, so we can continue to review.

 4              MR. KESSLER:        And the gentleman that,

 5   his house is shown here, he’s behind you?

 6              MR. STEINBERG:         He is directly, right,

 7   he is behind.

 8              MR. KESSLER:        And what’s his, what’s his

 9   elevation compared to yours?

10              MR. STEINBERG:         So he’s at

11   approximately, so his property line’s at the 390

12   mark, and then essentially it levels out from

13   there on Lafayette.

14              MR. KESSLER:        And you’re at 370, you

15   said?

16              MR. STEINBERG:         The building would be

17   set at 370, so essentially the top of the

18   building would be at that 390. So by setting it

19   closer to that, closer to him, you know, he would

20   obviously look over it, if he can even see

21   through the trees and the additional planting.

22              MR. KESSLER:        Are, are you making any

23   modifications to Lafayette at all or?

24              MR. STEINBERG:         So Lafayette is part of



                         Geneva Worldwide, Inc.
             228 Park Ave S - PMB 27669. New York, NY 10003

Page 74 Original page ↗

                                                               Page 74
1    February 3, 2026

 2   that overall roadway improvement that we talked

 3   about earlier this evening. So there will be a

 4   new right turn lane added to Lafayette. So

 5   there’s a, there’s a, a portion of the Evergreen

 6   site that’s being dedicated to the town to create

 7   that right turn lane. Right now it’s a single

 8   turn, single lane that handles all, all

 9   directions. So there’d be a new, one first lane

10   and then a right turn lane.

11               MR. KESSLER:        It certainly needs it

12   there.

13               MR. BIANCHI:        Yeah.

14               MR. KOBASA:        All of your mechanical, is

15   that all going to be on the roof? Where is that

16   going to be? Is that going to be internal?

17   Because I’m thinking if your mechanical’s on the

18   roof and that guy’s property is level with the

19   roof, he’s staring at a lot of HVAC.

20               MR. STEINBERG:         Yeah. So, right now the

21   logical place is to place it on the roof. That’s

22   so that it doesn’t have to be placed somewhere

23   else on the site. But we can continue to talk to

24   the architect about how that would be screened.



                          Geneva Worldwide, Inc.
              228 Park Ave S - PMB 27669. New York, NY 10003

Page 75 Original page ↗

                                                            Page 75
1    February 3, 2026

 2             MR. KOBASA:       Okay.

 3             MR. STEINBERG:        You know, with a parapet

 4   or other fencing. And then we are proposing some

 5   additional plantings within that buffer area.

 6             MR. KESSLER:       So you think the

 7   screening, those trees that you’re showing there,

 8   will block his view of the roof of your building?

 9             MR. STEINBERG:        Well, we can, we can

10   obviously use a mix of, of evergreens. There’s

11   also a significant amount of trees in that spot

12   today, but obviously --

13             MR. KEHOE:      Well beyond that landscaping

14   that you’re showing, there is a 30-foot no

15   disturb buffer.

16             MR. STEINBERG:        That’s within the 30-

17   foot, those that planting is within the 30-foot

18   buffer.

19             MR. KEHOE:      Oh, all right. So that

20   planting’s within the buffer?

21             MR. STEINBERG:        Within the 30, yes.

22             MR. KEHOE:      Okay.

23             MR. STEINMETZ:        However, Chris, my

24   understanding and Craig and Manny, we were both



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 76 Original page ↗

                                                            Page 76
1    February 3, 2026

 2   saying there’s presently a hundred foot

 3   separation between where we are and where the

 4   gentleman’s property.

 5            MR. KEHOE:       Well, between where, where

 6   his house is.

 7            MR. STEINMETZ:         Correct. Where his house

 8   is, correct. So my understanding is there is a

 9   fair amount of vegetation there now, and, and

10   Chris, Chris beat me to what I was going to say,

11   which is responding to Kevin, there is a 30 foot

12   area of non-disturbance where there will be a

13   vegetative, a buffer maintained. And we certainly

14   can look at and enhance it if -- we’ll do a line

15   of sight analysis to analyze the HVAC questions.

16   And it’s a legit question that we have to

17   understand. You have to understand, and I think

18   we can, as a result of the orientation of the

19   building, we should be able to mitigate that.

20            MR. KESSLER:        Right.

21            MR. KOBASA:        Okay.

22            MR. STEINMETZ:         But let us look at that.

23            MR. KESSLER:        And certainly some sound

24   bafflers, I would think you have part of this so



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 77 Original page ↗

                                                            Page 77
1    February 3, 2026

 2   that the sound goes --

 3            MR. STEINMETZ:         Correct.

 4            MR. KESSLER:        -- not in his direction.

 5   Any other comments? And this is, I know very

 6   preliminary. Staff will get this back and review

 7   it.

 8            MR. STEINMETZ:         Correct.

 9            MR. KESSLER:        You’ll come in with a

10   three-lot subdivision at some point?

11            MR. STEINMETZ:         Absolutely. And, and

12   just so you understand why the medical building

13   has now been submitted. We spent a fair amount of

14   time with staff, and I can let them speak to

15   their own comments and suggestions. The way the

16   MOD zoning was written by the town board, we are

17   required to have a medical use in there before

18   certificates of occupancy can be issued for any

19   residential use.

20            As I, as I foreshadowed at the last

21   meeting, and it’s, everybody knows one of the

22   nation’s preeminent home builders, Lennar Homes,

23   wants to come in and begin processing a townhouse

24   project. In order for them to do that and to make



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 78 Original page ↗

                                                            Page 78
1    February 3, 2026

 2   that a reality, we need to have some sense of the

 3   timing. Because, if they come in and are ready to

 4   build and sell townhouses, people may be lining

 5   up in Cortlandt saying, I want to buy one of

 6   these. Why won’t the town let me get a CO and

 7   move in? So we have attempted to determine that

 8   building the 10,000 square foot medical building,

 9   the medical supply, and the small medical office

10   will allow a much more rapid construction and

11   potential, CO on that building than would a

12   96,000 square foot assisted living. We’re excited

13   about Benchmark, but Benchmark’s going to take a

14   longer period of time. And the Santucci team

15   believes that they can get this building in

16   rapidly once it’s approved.

17            So that’s why we’re here with this one

18   now, and we appreciate the fact that your board

19   is beginning its review even though you do not

20   have a three-lot, or a 100-lot subdivision yet in

21   front of you. So thank you.

22            MR. MCKINLEY:         So this will be your,

23   this will be your first building operational?

24            MR. STEINMETZ:         That’s, I -- the first



                       Geneva Worldwide, Inc.
           228 Park Ave S - PMB 27669. New York, NY 10003

Page 79 Original page ↗

                                                              Page 79
1    February 3, 2026

 2   vertical building --

 3               MR. MCKINLEY:        First Building, to get --

 4               MR. STEINMETZ:        First vertical.

 5               MR. MCKINLEY:        -- a CO?

 6               MR. STEINMETZ:        Yes.

 7               MR. MCKINLEY:        Right. Yeah.

 8               MR. STEINMETZ:        The first construction

 9   operation will be clearing and grading for the

10   road.

11               MR. MCKINLEY:        Yes, Yeah, yeah.

12   Understood.

13               MR. STEINMETZ:        Thank you all. We have

14   nothing else for you affirmatively tonight.

15               MR. KESSLER:       Okay, if there’s nothing

16   else. Kevin?

17               MR. KOBASA:       I’d like to make a motion

18   to refer back to staff for memo.

19               MR. KESSLER:       Second, please.

20               MR. MCKINLEY:        Second.

21               MR. KESSLER:       And all the question. All

22   in favor?

23               MULTIPLE:      Aye.

24               MR. KESSLER:       Opposed?



                         Geneva Worldwide, Inc.
             228 Park Ave S - PMB 27669. New York, NY 10003

Page 80 Original page ↗

                                                                Page 80
1        February 3, 2026

2                 MR. STEINMETZ:         Thank you.

3                 MR. KOBASA:        The time is 7:28. Meeting’s

4       adjourned.

5                 MR. KESSLER:        Adjourned, thank you.

6   (The public board meeting concluded at 7:28 p.m.)




                           Geneva Worldwide, Inc.
               228 Park Ave S - PMB 27669. New York, NY 10003

Page 81 Original page ↗

                                                                      Page 81


                              CERTIFICATE OF ACCURACY



     I, Juliana Castano, certify that the foregoing

     transcript of the Board meeting of the Town of

     Cortlandt on February 3, 2026 was prepared using

     the required transcription equipment and is a true

     and accurate record of the proceedings.

     Certified By




        ________________________________________